Research & Development Tax Credit (RDTC) payment delays – an update

14 Jun 2022

HMRC have asked us to share the message below about the recent pausing of RDTC payments with our members:

Message from HMRC

We previously notified agents that we have paused some Research & Development Tax Credit (RDTC) payments while we investigate an increase in irregular claims. Our investigations are continuing, but we are now able to provide an update. 

To prevent abuse of the relief we will be enhancing our extensive compliance checks. These additional checks will mean our standard processing times will increase.  

For the vast majority of claims, we will aim to either pay the payable tax credit or contact you regarding the claim within 40 days. It is our ambition to return to our standard 28 day processing times as soon as we can. Our gov.uk guidance will be updated shortly. 

We wanted to share this update to notify legitimate claimants that their RDTC payments will take longer to be processed. We appreciate agents’ and claimants’ patience while we handle these claims and continue to offer the guidance below: 

  • To help us process your R&D payment quickly, please ensure you have completed all entries on the R&D section of your Corporation Tax return (CT600 form). 
  • Submitting additional information to support the claim, such as the R&D report will help HMRC process the claim quicker. 
  • Review the latest guidance on completing your CT600 form on GOV.UK 
  • If you submit a claim that is incorrect, inflated or fraudulent then you may be liable to a penalty. Read HMRC: standards for agents 

We ask R&D claimants to bear with us and kindly ask them not to contact the R&D helpline/mailbox to chase their claims. We also ask you not to contact any HMRC official about a claim. Instead, agents should check the company’s online account to check the status of their claim. 

We will continue to share updates when we have further information.